| Applicant | Project Well | Plan ID: | 291 |
| Status: | approved_accepted | Review Cycle end date: | 2010-08-26 |
| Name | Status | Start Date | Completion Date | Date of Last Report | Amount Assigned | |
|---|---|---|---|---|---|---|
| Arsenic free bore-dugwell (PW202) funded by Blue Planet Network and MSSCT | completed_late | 2010-11-01 | 2011-12-31 | 2012-11-02 | $1,160 | |
| Arsenic free bore-dugwell (PW201) funded by Blue Planet Network and MSSCT | completed_late | 2010-11-01 | 2011-12-31 | 2012-03-26 | $1,160 | |
| Arsenic free bore-dugwell (PW200) funded by Blue Planet Network and MSSCT | completed_late | 2010-11-01 | 2011-12-31 | 2013-09-10 | $1,160 | |
| Arsenic free bore-dugwell (PW199) funded by Blue Planet Network and MSSCT | completed_late | 2010-11-01 | 2011-12-31 | 2013-08-08 | $1,160 | |
| Arsenic free bore-dugwell (PW198) funded by Blue Planet Network and MSSCT | completed_late | 2010-11-01 | 2011-12-31 | 2013-08-08 | $956 | |
| Applicant | :   | Project Well |
| Status | : | approved_accepted |
| Country | : | INDIA Map |
| Amount Funded | :   | $5,596 |
| Funded By:- | ||
| Blue Planet Network | : | $5,596 |
Funds Used |
: | $5,596 |
Funds Available |
: | $0 |
| Number of Projects | : | 5 |
| Overall Start Date | : | TODO! |
| Overall Completion Date | : | TODO! |
| Date of Last Update | : | 2013-09-10 |