plan 410International Lifeline Fund: Projects for 2010

Summary

Proposal already approved and funded, this application is placeholder for importing existing projects

Background

Proposal already approved and funded, this application is placeholder for importing existing projects

Location

, , Uganda

Focus

Primary Focus: Drinking Water - Community
Secondary Focus: Sanitation - Community

People Getting Safe Drinking Water: 23,114

School Children Getting Water:

People Getting Sanitation: 0

People Getting Other Benefits:

Start Date: 2010-01-02

Completion Date: 2010-11-06

Technology Used:

Proposal already approved and funded, this application is placeholder for importing existing projects

Phases:

Community Organization:

Proposal already approved and funded, this application is placeholder for importing existing projects

Government Interaction:

Ancillary activities:

Other Issues:

Maintenance Revenue:

Maintenance Cost:

Metrics:

Prior art before metrics

Cost: $134,886

Proposal already approved and funded, this application is placeholder for importing existing projects

Co Funding Amount:

Community Contribution Amount:

Fund Requested: $133,560

Implementing Organization:

Name Status Completion Date Amount Assigned
Opwodorwot completed Jan 2010 $3,330
Atodi completed Jan 2010 $3,330
Adeknino completed Feb 2010 $5,220
Angwinyi completed Feb 2010 $3,330
Orem completed Mar 2010 $3,330
Atyena owee completed Apr 2010 $5,220
Ogengo completed May 2010 $3,330
Atingtwoo completed Jun 2010 $3,330
Acandano completed Jun 2010 $5,220
Abyenek completed Jul 2010 $3,330
Anaiober completed Jul 2010 $3,330
Aton completed Aug 2010 $3,330
Acandyang completed Oct 2010 $3,330
Akadoayubu completed Nov 2010 $5,220
Omyelo.onoro completed Nov 2010 $3,330
Agweng completed Nov 2010 $3,330
Dim Dem completed Apr 2010 $5,220
Ogetoiicok completed Jul 2010 $3,330
Akitepia completed Jul 2010 $3,330
Okoto completed Feb 2010 $5,220
Akamdini completed Jul 2010 $3,330
Amo-olel completed Jun 2010 $5,220
Itang completed Jul 2010 $3,330
Woromite completed May 2010 $3,330
Olago completed Jun 2010 $3,330
Alela completed Jul 2010 $3,330
Akaoidebe completed Jul 2010 $3,330
Acanata completed Jan 2010 $5,220
Janan completed Feb 2010 $3,330
Apitpit completed May 2010 $3,330
Owinyo completed Aug 2010 $5,220
Teilwa completed Jul 2010 $3,330
Akutu completed Mar 2010 $3,330
Awita completed Jun 2010 $3,330
Apurber completed Jan 2010 $3,330