plan 6141001 fontaines: Projects for 2012

Summary

Proposal already approved and funded, this application is placeholder for importing existing projects

Background

Proposal already approved and funded, this application is placeholder for importing existing projects

Location

, , Cambodia

Focus

Primary Focus: Capacity Building
Secondary Focus: Other

People Getting Safe Drinking Water: 7,975

School Children Getting Water:

People Getting Sanitation: 0

People Getting Other Benefits:

Start Date: 2012-01-25

Completion Date: 2014-12-30

Technology Used:

Proposal already approved and funded, this application is placeholder for importing existing projects

Phases:

Community Organization:

Proposal already approved and funded, this application is placeholder for importing existing projects

Government Interaction:

Ancillary activities:

Other Issues:

Maintenance Revenue:

Maintenance Cost:

Metrics:

Prior art before metrics

Cost: $322,000

Proposal already approved and funded, this application is placeholder for importing existing projects

Co Funding Amount:

Community Contribution Amount:

Fund Requested: $314,000

Implementing Organization:

Name Status Completion Date Amount Assigned
Cambodia Phase 2 - F2 complete_successful Mar 2013 $19,000
Cambodia Phase 2 - F3 complete_successful Jan 2013 $19,000
Cambodia Phase 2 - F4 complete_successful Jun 2013 $19,000
Cambodia Phase 2 - F5 complete_successful May 2013 $19,000
Cambodia Phase 2 - F6 complete_successful May 2013 $19,000
Cambodia Phase 2 - F7 complete_successful Mar 2013 $19,000
Cambodia Phase 2 - F8 complete_successful May 2013 $19,000
Cambodia Phase 2 - F9 complete_successful Feb 2013 $19,000
Cambodia Phase 2 - F10 complete_successful Feb 2013 $19,000
Cambodia Phase 3 - G1 in_progress Dec 2013 $19,000
Cambodia Phase 3 - G2 in_progress Dec 2013 $19,000
Cambodia Phase 3 - G3 in_progress Dec 2013 $19,000
Cambodia Phase 3 - G4 in_progress Dec 2013 $21,500
Cambodia Phase 3 - G5 in_progress Dec 2013 $21,500
Cambodia Phase 3 - G12 in_progress Dec 2014 $21,500
Cambodia Phase 3 - G24 in_progress Dec 2014 $21,500
Madagascar Phase 1 - B2 in_progress Feb 2013 $0
Madagascar Phase 1 - B4 in_progress Jul 2013 $0
Madagascar Phase 1 - B5 in_progress Jul 2013 $0