Repairing the well at the Ahmadiyya Primary School in Malaisoko with over 970 beneficiaries

Narrative

The only deviation is that we did not start as was proposed due to funding process.

  • Idriss Kamara of Safer Future Youth Development Project
    • confidential
    Implementation Status: in_progress Wed 25 Jul 2007, Over 17 Years ago

    Plumping will be done by end of the month

    The 100.000 litres tank from the first allocation is nearly completed. Only the pipes and pump have to be installed. The material was already bought and delivered to the site.

    The financial report therefore is already available but has to wait for the narrative that will contain pictures from the completed tank. We are looking forward to do the plumbing before the end of this month.

  • Impact Assessment (M&E) Phase Project completed on 16 Feb, 2006 Implementation Phase
  • Implementation Phase Project started on 16 Jan, 2006 Preparation Phase

Repairing the well at the Ahmadiyya Primary School in Malaisoko with over 970 beneficiaries

Narrative

The only deviation is that we did not start as was proposed due to funding process.

Other Issues

Unusual and unexpected issues faced during project execution

the tank is working well and the management committee set up is having the cooperation of the people.

Learnings

Knowledge of project and process for sharing

Water brings improvement in sanitation and the general well being of people.

Impact

People Getting Safe Drinking Water: 970

School kids, community of Malaisoko as well as surrounding communities

School Children Getting Water: 150

People Getting Other Benefits: 15

People who got payment in the work they did during the construction of the tank.

Maintenance/Operating Costs Annual, in US$: $20

Creating and measuring long-term impact

Funding

funded:
$2,500
Final Cost:
$2,500
edit $2,500:
Blue Planet Network

Plan/Proposal