Helping 229 households from An Thanh Thuy,Cho Gao in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong).

Narrative

Historical Data Imported.

Helping 229 households from An Thanh Thuy,Cho Gao in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong). The following methods were utilized for treatment: . The following chemicals are added:

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2010 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2010 Preparation Phase

Helping 229 households from An Thanh Thuy,Cho Gao in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong).

Narrative

Historical Data Imported.

Helping 229 households from An Thanh Thuy,Cho Gao in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong). The following methods were utilized for treatment: . The following chemicals are added:

Impact

People Impacted: 916

People Getting Safe Drinking Water: 916

229.0

Member Specific Project Data

Water Source: G
Project Type: U
Treatment Type:
Chemicals Added:
Length of Pipe System (m): N/A
Comments on Status: Good
Comments on Solutions: Pipeline extension (1,5 km) for 500 more HHs connection; PE want to hace 2 wells drilling (395m deep for each)
Notes: Good
Cost in Local Currency: 808179101.172063

Funding

funded:
$37,589
Community:
$7,933
Final Cost:
$74,461
edit $37,589:
GPOBA

Plan/Proposal