Model ECOSAN toilets were constructed for 9 nos. of Households in this village. The women from these households are members of women SHGs guided and monitored by Ekoventure. The women were arranged with loans from the SHGs towards their contribution.

  • Tamaraiselvi V of Ekoventure
    • confidential
    • SMS
    Implementation Status: in_progress Thu 06 Sep 2012, Over 11 Years ago

    indru kalanivasal valliyamai,amutha,piramila vittu toilet open seiythom.

  • Tamaraiselvi V of Ekoventure
    • confidential
    • SMS
    Implementation Status: in_progress Wed 05 Sep 2012, Over 11 Years ago

    indru kalanivasal mariyammal vittu toilet open seiythom.

  • Tamaraiselvi V of Ekoventure
    • confidential
    • SMS
    Implementation Status: in_progress Thu 30 Aug 2012, Over 11 Years ago

    Kazhanivasal 7 members vittukku sendru toilet parthu vanthean.

  • S. Pushpalatha of Ekoventure
    • confidential
    Implementation Status: completed Mon 03 Jan 2011, About 13 Years ago

    ECOSAN toilets effectively utilised

    All the 9 nos. of ECOSAN toliets were visited to monitor. All the families have got convinced in using this type - dry pit toilet. The toilets are kept clean and no bad odour was noticed in any of the toilets.

  • Impact Assessment (M&E) Phase Project completed on 30 Jun, 2010 Implementation Phase
  • Implementation Phase Project started on 1 Sep, 2009 Preparation Phase

Model ECOSAN toilets were constructed for 9 nos. of Households in this village. The women from these households are members of women SHGs guided and monitored by Ekoventure. The women were arranged with loans from the SHGs towards their contribution.

Impact

People Impacted: 45

People Getting Sanitation: 45

9 families - approximately 45 members got sanitation facilities

People Getting Other Benefits: 3

The Masons were trained in the construction of ECOSAN toilets.

Funding

funded:
$1,960
Community:
$506
Final Cost:
$2,972