Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.

Narrative

The new site for borewell #PW203 is in Jangolpur village of Baduria block of N 24 Parganas district. This land is donated by Wahed Mondol to the community to construct the bore-dugwell.
__________________________________
31st December: Boring and digging is complete. Housing is ongoing. Photo is pending.

___________________
CANCELLED SITE AFTER PILOT TEST.
This site #PW205, is in Muslim para of Kadar Gaji village of Baduria block of N 24 Parganas district got cancelled after doing the pilot test to check the sediment.

This year there is a delay in the construction due to the following reasons:
1. during april and may no village meetings could be held because of assembly election in the state election;
2. many sites were selected and village meetings were held several months before the construction. Many sites were cancelled because of pipelines that the local panchayet came to know about later. In fact sites in two blocks, Haringhata and Bashirhat have been replaced by sites in Baduria and Swarupnagar.
3. During pilot tests due to non availability of water bearing sand layer and family or neigborly disputes by now 22 sites been cancelled.
4. At every new site village meetings are being held that leads to delay too.

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed_late Sat 22 Feb 2014, About 10 Years ago

    good water 50mltheoline 18ft water 8familier 42people

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed_late Sat 04 Jan 2014, Over 10 Years ago

    turbid water

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed_late Tue 17 Dec 2013, Over 10 Years ago

    give the hand over packege

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed_late Thu 10 Oct 2013, Over 10 Years ago

    I am giving arsenic report and handover folder. and also given at PW# 204, 205, 206, 207, 212, 228, 229.

  • Suparna Mondol of Project Well
    • confidential
    • SMS
    Implementation Status: completed_late Wed 18 Sep 2013, Over 10 Years ago

    We went to inspect the dugwell no- pw-205.

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed_late Tue 09 Jul 2013, Almost 11 Years ago

    pw205 we are doing healthmetting m3 f6 c2

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed Thu 01 Nov 2012, Over 11 Years ago

    Laltu and myself changed the washer and plunger of the handpump cost Rs.115. The community will start using again.

  • Laltu Mirza of Project Well
    • confidential
    • SMS
    Implementation Status: completed Thu 01 Nov 2012, Over 11 Years ago

    Farida and myself done maintenance: changed washer and plunger of the handpump.

  • Meera Hira-Smith of Project Well
    • confidential
    Implementation Status: completed_late Tue 20 Mar 2012, About 12 Years ago

    Picture of the construction being complete is still pending.

    Picture of the construction being complete is still pending.

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2011 Implementation Phase
  • Implementation Phase Project started on 30 Nov, 2010 Preparation Phase

Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.

Narrative

The new site for borewell #PW203 is in Jangolpur village of Baduria block of N 24 Parganas district. This land is donated by Wahed Mondol to the community to construct the bore-dugwell.
__________________________________
31st December: Boring and digging is complete. Housing is ongoing. Photo is pending.

___________________
CANCELLED SITE AFTER PILOT TEST.
This site #PW205, is in Muslim para of Kadar Gaji village of Baduria block of N 24 Parganas district got cancelled after doing the pilot test to check the sediment.

This year there is a delay in the construction due to the following reasons:
1. during april and may no village meetings could be held because of assembly election in the state election;
2. many sites were selected and village meetings were held several months before the construction. Many sites were cancelled because of pipelines that the local panchayet came to know about later. In fact sites in two blocks, Haringhata and Bashirhat have been replaced by sites in Baduria and Swarupnagar.
3. During pilot tests due to non availability of water bearing sand layer and family or neigborly disputes by now 22 sites been cancelled.
4. At every new site village meetings are being held that leads to delay too.

Learnings

Knowledge of project and process for sharing

Construction of bore-dugwell, boring and digging, should complete before the monsoon or rainy season. We have learnt that even after boring is completed, digging cannot be done when the water table is high without using heavy duty water pump. However, low ordinary pump is used when the water to be pumped out is maximum 4 feet in the dugwell.

Impact

People Getting Safe Drinking Water: 40

Registers will be created as soon as the community starts using the water from this bore-dugwell.

Maintenance/Operating Costs Annual, in US$: $40

Creating and measuring long-term impact

Implementer: Project Well & Aqua Welfare Society

Aqua Welfare Society (AWS) is the partner NGO of Project Well. Their office is based in North 24 Parganas. The seven honorary board members are located in Kolkata. New field workers have been engaged mainly for the surveillance program. There is one project manager, one technical manager, one awareness program manager, two technical assistants, one maintenance assistant, one assistant for data entry, one account assistant and three field workers; three more field workers will be hired. All field staff are constantly interacting with the villagers and beneficiaries, training the users on well maintenance, organizing village meetings and health meetings. The project manager visits the villages three to four times a week and works alongside the field workers, meeting with government officials and villagers, selecting sites, coordinating well construction, sending reports to Project Well and meeting with the members AWS to keep the projects running. The awareness programmer is in charge of conducting public education programs in the communities and educational institutions, which is the other component that makes our program sustainable.

Funding

funded:
$1,160

Plan/Proposal