Project Name:
RWHT for 2 rural schools in Mamama and Makande
Attached to Project Report:
Construction works complete
Title:
Construction of filtering tank
Description:
The fetched rainwater is first diverted to a filtering tank, which can easily be accessed and cleaned.
Attachments
Roof constru...
Roof construction
It is crucial to use enough iron-rods for the roof in order to be able to carry the heavy weight of the cement and of course of people standing on top.
Completed ro...
Completed roof
We always make sure that the contractor constructs the surface of the roof in a way that water doesn't settle there.
Fixing of Co...
Fixing of Collectors
To collect the rainwater we use PVC pipes, which are fixed all along the roof.
Running Water
Running Water
As soon as the collectors are fixed and connected, the rainwater is running. It is important to check the fixing-wire sometimes, as the pipes brake easily if they fall down.