Project Name:
RWHT for 2 rural schools in Mamama and Makande
Applicant:
Safer Future Youth Development Project
Current Status:
In-progress
Application ID:
42
Attached to:
Construction works complete
Title:
Fixing of Collectors
Description:
To collect the rainwater we use PVC pipes, which are fixed all along the roof.
Attachments
Roof constructio...
Roof construction
It is crucial to use enough iron-rods for the roof in order to be able to carry the heavy weight of the cement and of course of people standing on top.
Completed roof
Completed roof
We always make sure that the contractor constructs the surface of the roof in a way that water doesn't settle there.
Construction of ...
Construction of filtering tank
The fetched rainwater is first diverted to a filtering tank, which can easily be accessed and cleaned.
Running Water
Running Water
As soon as the collectors are fixed and connected, the rainwater is running. It is important to check the fixing-wire sometimes, as the pipes brake easily if they fall down.