Report: LW7 Development of Backup Borewell #2

A borewell had been constructed on the north end at 2nd cross of 12th main. This was considered a backup in case the primary borewell fails. This add-on project installed a pump and all the piping required to the bottom of the main overhead tank.

A met

2009-03-01
2009-12-04
$0
$1,000
$1,000
0

No new people getting drinking water.

0

0

0

Water - Community
Drinking Water - Community

$0

LWORA

Project Summary

Project ID 119
Owner : Blue Planet Network
Country : India
Go to : Application (Proposal)
Status : Completed

Project Verification

Self Verified? : No
By 3rd Party? : No

Funding

Photos and Documents

  • No attachments yet

Main Project Report

Implementation Phase Reports (0)

  • None

Operating Status Reports (0)

  • None

Peer Reports (0)

  • None

Visitor Reports (0)

  • None

Have you visited this project?