The funding was received only on 15th March 2011. Siince there was Assembly elections and Model code of conduct was in action, meetings involving women SHGs could not be conducted till 18th May 2011. The project was actively taken up from 20th May 2011.
Immediately after the initial sequence of awareness meetings, the women SHG members were taken up for an exposure visit to the existing ECOSAN toilet. 50 women participated. We have received 60 nos of applications for the ECOSAN toilets from the participants.
In the application it was proposed to construct 50 nos of ECOSAN toilets. But during the period of 8 months from the date of application, the cost price of important raw materials like cement, river sand, bricks has increased manifold. Also the mason wages has doubled and hence with the available budget it would be possible to construct 42 nos. only. The revised budget is attached herewith.