Report: D2W2: Wamba DEB Primary School Well

Funded by the Ridgestone Foundation, Pittsburgh Children's Foundation, Ruth & Charles Hopping, The Samburu Project drilled and installed a shallow well equipped with a handpump in this community.

2007-07-01
2007-07-15
$13,000
$1,850
$14,850
1,669
1,000

669

The main objective of the project is to provide clean, safe drinking water for the school.

0

1,000

Drinking Water - Community
Sanitation - Community

$419

Project Summary

Project ID 395
Owner : The Samburu Project
Country : Kenya
Go to : Application (Proposal)
Status : Completed

Project Verification

Self Verified? Yes (3 times)
Last On : Mon, 30 May, 2011
(almost 4 years after completion)
By 3rd Party? : No

Funding

Site(s) (1)

Main Project Report

Implementation Phase Reports (0)

  • None

Operating Status Reports (3)

Peer Reports (0)

  • None

Visitor Reports (0)

  • None

Have you visited this project?