The activities implemented were - (i) Construction of sanitation unit with one common toilet 4 urinals (2 urinals each for boys and girls respectively) (ii) a drinking water tank of 2000 capacity has been constructed (through govt funds). (iii) Trees plantation in school campus and surrounding open area of school. (iv) Health and sanitation education to school children and teachers.
Under the school drinking water and sanitation project, the drinking water connection has been provided to the school and the water is being stored in the newly constructed water storage tank which is constructed under the Govt. funds having the capacity of 2000 lit. Under BPR, construction, toilet unit having 1 toilet and 2 urinals each for boys and girls has been constructed. A separate water storage tank of 500 lits capacity has been constructed for the toilet unit and separate water connection has been provided to the water tank.
Under the tree plantation activity, the contour trenches have been excavated in the surrounding area of the school of approximately 15,000 sq.ft and a plantation of 3,000 trees have been made. Similarly in the school premises about 150 trees have been planted.
There are no changes or deviations in the original plan. In the original plan, a budget of 375 $ was sanctioned for the construction of drinking water storage tank for the school. Through the efforts of the school committee the government funds have been accessed for the construction of school water storage tank. Therefore there is a balance of USD 324 which is unspent. This amount would be used for the plantation gap refilling.