The project was finished two weeks early with all of the original elements of the project completed and functioning. In consultation with the village water committee and Rahesh the plan is to capture another spring site and repair a large public water station. The project should be finished by the end of Jan.
| Project ID | : | 89 |
| Owner | : | Agua Para La Salud (APLS) |
| Country | : | Guatemala |
| Go to | : | Application (Proposal) |
| Status | : | Complete - Success, Late |
| Self Verified? | : | No |
| By 3rd Party? | : | No |
By Lynn Roberts of Agua Para La Salud (APLS) on Thu, 15 Jan, 2009