Progress/Status Report | Relayout of the sewage line

Complete - Successful
Thursday, 15 April, 2010

This project will never finish!

The line east of the STP down 2nd Main has always been a problem. Most of it is lower than STP and thus has been partially responsible for smell and other issues.

3 measurements of the entire line were taken and a plan to raise the line is attached. The problem is that one of the homes has a low sewage line inlet so it needs to be raised.

The plan is to lay the new line on top of the old one and then start blocking the old line and raising the floor of all the existing chambers.

Rajesh Shah

Project Summary

Project ID 94
Owner : Blue Planet Network
Country : India
Go to : Application (Proposal)
Status : Complete - Success, Late

Project Verification

Self Verified? Yes (4 times)
Last On : Thu, 15 Apr, 2010
(12 months after completion)
Verified Status : Does not match project status
By 3rd Party? : No

Funding

Photos and Documents

  • No attachments yet

Main Project Report

Operating Status Reports (4)

Attachments

(For All Implementation Phase Reports)

Peer Reports (0)

  • None

Visitor Reports (0)

  • None

Have you visited this project?