This project will never finish!
The line east of the STP down 2nd Main has always been a problem. Most of it is lower than STP and thus has been partially responsible for smell and other issues.
3 measurements of the entire line were taken and a plan to raise the line is attached. The problem is that one of the homes has a low sewage line inlet so it needs to be raised.
The plan is to lay the new line on top of the old one and then start blocking the old line and raising the floor of all the existing chambers.
| Project ID | : | 94 |
| Owner | : | Blue Planet Network |
| Country | : | India |
| Go to | : | Application (Proposal) |
| Status | : | Complete - Success, Late |
| Self Verified? | : | Yes (4 times) |
| Last On | : |
Thu, 15 Apr, 2010
(12 months after completion) |
| Verified Status | : | Does not match project status |
| By 3rd Party? | : | No |
By Rajesh Shah of Blue Planet Network on Wed, 01 Apr, 2009
By Rajesh Shah of Blue Planet Network on Sun, 15 Mar, 2009
By Rajesh Shah of Blue Planet Network on Tue, 17 Feb, 2009
By Rajesh Shah of Blue Planet Network on Thu, 15 Apr, 2010
By Rajesh Shah of Blue Planet Network on Tue, 23 Mar, 2010
By Rajesh Shah of Blue Planet Network on Sat, 06 Mar, 2010
By Rajesh Shah of Blue Planet Network on Fri, 15 May, 2009