Projects of: "Well construction in 4 villages in Samburu District (D1W1, D1W2, D1W3 & D1W4)"

Applicant The Samburu Project Plan ID: 340
Status: approved_accepted Review Cycle end date: 2006-01-06

Name Status Start Date Completion Date Date of Last Report Amount Assigned
D1W1: Lendadapoi Well completed 2006-07-01 2006-07-15 2012-10-22 $10,000
D1W2: Lopesiwo 1 Well completed 2006-07-01 2006-07-15 2012-05-14 $10,000
D1W3: Lokuniyani Well completed 2006-07-01 2006-07-15 2012-08-27 $13,000
D1W4: Lkisin Well completed 2006-07-01 2006-07-15 2012-05-16 $10,000

Application Summary

Applicant :   The Samburu Project
Status : approved_accepted
Country : KENYA Map

Funding

Amount Funded :   $52,000
Funded By:-
Anonymous : $52,000
Funds Used
: $43,000
Funds Available
: $9,000

Projects Summary of Application

Number of Projects : 4
Overall Start Date : TODO!
Overall Completion Date : TODO!
Date of Last Update : 2012-10-22