Monitoring STP operations, discharge, and reuse - repairing and enhancing STP

Narrative

Encourage the community to fix their STP which is not working

Sewage Treatment Plant Data

No specific STP design or operating data
    • Third Party
    Mannat Bhalla About 4 Years after completion 11 Feb, 2016

    STP

    Status: Complete - Successful

    Operating Status:

    It was very informative, At least some places in India are working toward making our country a better place to live in. We visited 3 sites. The first one was Rainbow drive where we saw how their community disposed their garbage and how sewage treatment plants work. The second was a place outside a building where we saw the sewage just flowing outside their building and we saw poor children who were living right next to it and they didn't care about their health. This journey made me be more considerate about my surroundings.

    • Third Party
    Ananya Gupta About 4 Years after completion 11 Feb, 2016

    STP visit

    Status: Complete - Successful

    Operating Status:

    It was a very interesting and innovative trip. We visited 3 sites. We learnt a lot about how people dispose their garbage and how sewage treatment plants work. It was a trip that was that was very educational. Its crazy how people treat their sewage in such a neglected manner. It has taught me to be more considerate about my surroundings and look beyond my bubble

    • peer
    Dr. Surendra Kulkarni ( Lake Shore Homes ) About 4 Years after completion 5 Feb, 2016

    SJR Verity's raw sewage coming out of their layout

    Status: Complete - Unsuccessful

    Operating Status:

    SJR Verity's raw sewage coming out of their layout into the storm water drain. Impact is a very smelly main road and then the sewage turns and heads towards other neighbours.

    • Thumb_img-20160210-wa0005p
    • Thumb_img-20160210-wa0007p
    • Thumb_img-20160210-wa0004p
    • Thumb_img-20160210-wa0002p
    • Thumb_img-20160210-wa0003p
    • Thumb_img-20160210-wa0006p
    • peer
    Regional Officer ( KSPCB ) Almost 4 Years after completion 9 Dec, 2015

    Notice No. PCB/RO/BOM/DEO/2015-16/11582

    Status: Complete - Unsuccessful

    Operating Status:

    "Non-Compliance under the provisions of Water(Prevention and Control of Pollution) Act,1974 by your apartment at the above said address and returning of CFO application-reg "
    With reference to the above subject, your attention is invited to the letter attached.
    Regional Officer, RO-Bommanahalli

    • Pdf KSPCB_No...
  • Impact Assessment (M&E) Phase Project completed on 5 Feb, 2012 Implementation Phase
  • Implementation Phase Project started on 9 May, 2011 Preparation Phase

Monitoring STP operations, discharge, and reuse - repairing and enhancing STP

Narrative

Encourage the community to fix their STP which is not working

Sustainability

Creating and measuring long-term impact

Monthy costs in energy and staff for all water, sewage treatment, and general activies. Need to get economics of treatment only.

Learnings

Knowledge of project and process for sharing

Constant complaints from neighbours has no effect

Impact

People Impacted: 1000

Maintenance/Operating Costs Annual, in US$: $1000

Creating and measuring long-term impact

Monthy costs in energy and staff for all water, sewage treatment, and general activies. Need to get economics of treatment only.

Funding

Funded:
$8,000
Community:
$8,000
Final Cost:
$8,000
$8,000:
Self

Plan/Proposal