| Applicant | The Samburu Project | Plan ID: | 312 |
| Status: | approved_accepted | Review Cycle end date: | 2011-09-21 |
| Name | Status | Start Date | Completion Date | Date of Last Report | Amount Assigned | |
|---|---|---|---|---|---|---|
| D6W9: Golgoltim Well (fka Lenchekut 1) | completed | 2012-08-02 | 2013-01-10 | 2013-01-10 | $14,000 | |
| D6W8: Lempuranai Well (fka Lenchekut 2) | completed | 2012-08-04 | 2013-01-10 | 2013-01-10 | $14,000 | |
| Applicant | :   | The Samburu Project |
| Status | : | approved_accepted |
| Country | : | KENYA Map |
| Amount Funded | :   | $28,000 |
| Funded By:- | ||
| MSSCT | : | $28,000 |
Funds Used |
: | $28,000 |
Funds Available |
: | $0 |
| Number of Projects | : | 2 |
| Overall Start Date | : | TODO! |
| Overall Completion Date | : | TODO! |
| Date of Last Update | : | 2013-01-10 |