| Applicant | The Samburu Project | Plan ID: | 313 |
| Status: | approved_accepted | Review Cycle end date: | 2010-08-26 |
| Name | Status | Start Date | Completion Date | Date of Last Report | Amount Assigned | |
|---|---|---|---|---|---|---|
| D5W1: Upper Margwe Well | completed | 2011-07-06 | 2011-09-02 | 2013-05-14 | $13,000 | |
| D5W2: Sordo Namunyak Well | completed | 2011-07-07 | 2011-09-05 | 2012-05-12 | $13,000 | |
| D5W8: Laresoro Well | completed | 2011-07-18 | 2011-11-05 | 2012-05-25 | $13,000 | |
| D5W9: Supalek Well | completed | 2011-07-18 | 2011-11-08 | 2012-05-23 | $13,000 | |
| Applicant | :   | The Samburu Project |
| Status | : | approved_accepted |
| Country | : | KENYA Map |
| Amount Funded | :   | $78,000 |
| Funded By:- | ||
| Self | : | $78,000 |
Funds Used |
: | $52,000 |
Funds Available |
: | $26,000 |
| Number of Projects | : | 4 |
| Overall Start Date | : | TODO! |
| Overall Completion Date | : | TODO! |
| Date of Last Update | : | 2013-05-14 |