| Applicant | The Samburu Project | Plan ID: | 351 |
| Status: | approved_accepted | Review Cycle end date: | 2010-01-05 |
| Name | Status | Start Date | Completion Date | Date of Last Report | Amount Assigned | |
|---|---|---|---|---|---|---|
| D4W1: Laga Well | completed | 2010-04-01 | 2010-04-15 | 2012-05-23 | $13,000 | |
| D4W2: Treetop Well | completed | 2010-04-01 | 2010-04-15 | 2012-06-24 | $13,000 | |
| D4W3: Sordo Well | completed | 2010-04-01 | 2010-04-15 | 2012-06-12 | $13,000 | |
| D4W4: Lbaa Onyokie 2 Well | completed | 2010-04-01 | 2010-04-15 | 2022-07-07 | $13,000 | |
| D4W5: Lbaa lo Ltepes 2 Well | completed | 2010-04-01 | 2010-04-15 | 2012-08-03 | $13,000 | |
| D4W6: Lbaa lo Ltepes 3 Well | completed | 2010-04-01 | 2010-04-15 | 2012-05-16 | $13,000 | |
| D4W7: Ldupai/Jerusalem Well | completed | 2010-04-01 | 2010-04-30 | 2012-05-21 | $13,000 | |
| D4W8: SHERP Well | completed | 2010-05-01 | 2010-05-15 | 2011-02-25 | $13,000 | |
| Applicant | :   | The Samburu Project |
| Status | : | approved_accepted |
| Country | : | KENYA Map |
| Amount Funded | :   | $104,000 |
| Funded By:- | ||
| Anonymous | : | $104,000 |
Funds Used |
: | $104,000 |
Funds Available |
: | $0 |
| Number of Projects | : | 8 |
| Overall Start Date | : | TODO! |
| Overall Completion Date | : | TODO! |