plan 484El Porvenir: Projects for 1996

Summary

Proposal already approved and funded, this application is placeholder for importing existing projects

Background

Proposal already approved and funded, this application is placeholder for importing existing projects

Location

, , Nicaragua

Focus

Primary Focus: Sanitation - Households
Secondary Focus: Hygiene Education

People Getting Safe Drinking Water: 1,076

School Children Getting Water:

People Getting Sanitation: 826

People Getting Other Benefits:

Start Date: 1996-01-01

Completion Date: 1996-12-31

Technology Used:

Proposal already approved and funded, this application is placeholder for importing existing projects

Phases:

Community Organization:

Proposal already approved and funded, this application is placeholder for importing existing projects

Government Interaction:

Ancillary activities:

Other Issues:

Maintenance Revenue:

Maintenance Cost:

Metrics:

Prior art before metrics

Cost: $3,174

Proposal already approved and funded, this application is placeholder for importing existing projects

Co Funding Amount:

Community Contribution Amount:

Fund Requested: $3,174

Name Status Completion Date Final Cost
Bacacan completed Dec 1996 1,115
Bacacan completed Dec 1996 0
Plan de Monte completed Dec 1996 0
Totumblita completed Dec 1996 0
Mombacho completed Dec 1996 0
La Calamidad completed Dec 1996 0
San Esteban completed Dec 1996 672
Mombacho completed Dec 1996 0
Plan de Monte completed Dec 1996 0
La Montanita completed Dec 1996 1,387
Mombacho completed Dec 1996 0