plan 486El Porvenir: Projects for 1998

Summary

Proposal already approved and funded, this application is placeholder for importing existing projects

Background

Proposal already approved and funded, this application is placeholder for importing existing projects

Location

, , Nicaragua

Focus

Primary Focus: Sanitation - Households
Secondary Focus: Hygiene Education

People Getting Safe Drinking Water: 1,310

School Children Getting Water:

People Getting Sanitation: 1,146

People Getting Other Benefits:

Start Date: 1998-01-01

Completion Date: 1998-12-31

Technology Used:

Proposal already approved and funded, this application is placeholder for importing existing projects

Phases:

Community Organization:

Proposal already approved and funded, this application is placeholder for importing existing projects

Government Interaction:

Ancillary activities:

Other Issues:

Maintenance Revenue:

Maintenance Cost:

Metrics:

Prior art before metrics

Cost: $11,848

Proposal already approved and funded, this application is placeholder for importing existing projects

Co Funding Amount:

Community Contribution Amount:

Fund Requested: $11,848

Name Status Completion Date Final Cost
Cerro Grande completed Dec 1998 0
El Aguacate completed Dec 1998 3,968
San Antonio completed Dec 1998 0
San Antonio completed Dec 1998 0
Las Pencas completed Dec 1998 0
Las Alvellanas completed Dec 1998 1,880
Nancital completed Dec 1998 0
Pedro Joaquin Chamorro completed Dec 1998 0
San Isidro completed Dec 1998 1,000
Bacacan Maunica completed Dec 1998 2,800
Las Arenitas/La Chilena completed Dec 1998 0
Hato de la Virgen completed Dec 1998 1,341
El Cebollin completed Dec 1998 0
El Cebollin completed Dec 1998 0
La Remonta completed Dec 1998 280
Las Pozas completed Dec 1998 0
San Juanillo completed Dec 1998 0
Las Delicias completed Dec 1998 0
Sonzapote completed Dec 1998 579