A borewell had been constructed on the north end at 2nd cross of 12th main. This was considered a backup in case the primary borewell fails. This add-on project installed a pump and all the piping required to the bottom of the main overhead tank.

A met

  • Rajesh Shah of Peer Water Exchange
    • confidential
    • Mobile
    Operating Status: no_data Sun 20 Sep 2020, About 4 Years ago

    None

    None

  • Impact Assessment (M&E) Phase Project completed on 4 Dec, 2009 Implementation Phase
  • Implementation Phase Project started on 1 Mar, 2009 Preparation Phase

A borewell had been constructed on the north end at 2nd cross of 12th main. This was considered a backup in case the primary borewell fails. This add-on project installed a pump and all the piping required to the bottom of the main overhead tank.

A met

Impact

Funding

Community:
$1,000
Final Cost:
$1,000

Plan/Proposal