Community Latrine Project- Double Pit

Narrative

imported data from historical project list

    • confidential
    Martha Oneida Hernández ( El Porvenir ) Over 3 Years after completion 21 Jun, 2013

    Note for internal use

    • confidential
    Martha Oneida Hernández ( El Porvenir ) Almost 3 Years after completion 30 Nov, 2012

    Note for internal use

    • confidential
    Martha Oneida Hernández ( El Porvenir ) Almost 3 Years after completion 12 Nov, 2012

    Note for internal use

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2009 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2009 Preparation Phase

Community Latrine Project- Double Pit

Narrative

imported data from historical project list

Sustainability

Creating and measuring long-term impact

imported data from historical project list

Other Issues

Unusual and unexpected issues faced during project execution

imported data from historical project list

Learnings

Knowledge of project and process for sharing

imported data from historical project list

Impact

People Impacted: 181

People Getting Sanitation: 181

Implementer: El Porvenir

Funding

Funded:
$12,750
Final Cost:
$12,750
$12,750:
Anonymous

Plan/Proposal