Helping 189 households from ,Thuong Tin in Vietnam access drinking water. The system is managed by the Provincial Water Company.

Narrative

Historical Data Imported.

Helping 189 households from ,Thuong Tin in Vietnam access drinking water. The system is managed by the Provincial Water Company. The following methods were utilized for treatment: . The following chemicals are added:

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2007 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2008 Preparation Phase

Helping 189 households from ,Thuong Tin in Vietnam access drinking water. The system is managed by the Provincial Water Company.

Narrative

Historical Data Imported.

Helping 189 households from ,Thuong Tin in Vietnam access drinking water. The system is managed by the Provincial Water Company. The following methods were utilized for treatment: . The following chemicals are added:

Sustainability

Creating and measuring long-term impact

Electro-mechanical (pumps, etc.), Groundwater availability, , ,

Other Issues

Unusual and unexpected issues faced during project execution

Main Problems: Groundwater quality,Electro-mechanical (pumps, etc.),Treatment,Storage tank/construction,Distribution network, Main Reason for Problem: ,EMW planning, design & implementation,Poor (technical) maintenance,Funding/financial problems,Other

Impact

People Impacted: 495

People Getting Safe Drinking Water: 495

189.0

Member Specific Project Data

Water Source: G
Project Type: N
Treatment Type:
Chemicals Added:
Length of Pipe System (m): 2548
Comments on Status:
Comments on Solutions:
Notes: still operates. However the filtration system is old,Local water managers suggest EMW to upgrade the filtration system for better water quality
Cost in Local Currency: 537500000

Funding

funded:
$25,000
Final Cost:
$25,000
edit $25,000:
Coca Cola

Plan/Proposal