Helping 357 households from Binh Phu,Thang Binh in Vietnam access drinking water. The system is managed by a local Cooperative.

Narrative

Historical Data Imported.

Helping 357 households from Binh Phu,Thang Binh in Vietnam access drinking water. The system is managed by a local Cooperative. The following methods were utilized for treatment: pressure. The following chemicals are added: chlorine

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2007 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2008 Preparation Phase

Helping 357 households from Binh Phu,Thang Binh in Vietnam access drinking water. The system is managed by a local Cooperative.

Narrative

Historical Data Imported.

Helping 357 households from Binh Phu,Thang Binh in Vietnam access drinking water. The system is managed by a local Cooperative. The following methods were utilized for treatment: pressure. The following chemicals are added: chlorine

Impact

People Impacted: 1320

People Getting Safe Drinking Water: 1320

357.0

Member Specific Project Data

Water Source: G
Project Type: N
Treatment Type: pressure
Chemicals Added: chlorine
Length of Pipe System (m): 10870
Comments on Status: Good
Comments on Solutions:
Notes:
Cost in Local Currency: 941119500

Funding

funded:
$43,773
Community:
$8,850
Final Cost:
$52,623
edit $43,773:
GPOBA

Plan/Proposal