Helping 831 households from Phong Son,Phong Dien in Vietnam access drinking water. The system is managed by a local Cooperative.
Narrative
Historical Data Imported.
Helping 831 households from Phong Son,Phong Dien in Vietnam access drinking water. The system is managed by a local Cooperative. The following methods were utilized for treatment: pressure. The following chemicals are added: chlorine & alum
- Impact Assessment (M&E) Phase Project completed on 31 Dec, 2007 Implementation Phase
- Implementation Phase Project started on 1 Jan, 2008 Preparation Phase
Helping 831 households from Phong Son,Phong Dien in Vietnam access drinking water. The system is managed by a local Cooperative.
Narrative
Historical Data Imported.
Helping 831 households from Phong Son,Phong Dien in Vietnam access drinking water. The system is managed by a local Cooperative. The following methods were utilized for treatment: pressure. The following chemicals are added: chlorine & alum
Sustainability
Creating and measuring long-term impact
Groundwater availability, , , ,
Other Issues
Unusual and unexpected issues faced during project execution
Main Problems: , , ,Groundwater quality,Distribution network, Main Reason for Problem: , ,EMW planning, design & implementation,Poor (technical) maintenance,Other
Impact
People Impacted: 3739
People Getting Safe Drinking Water: 3739
831.0