Helping 647 households from Binh Thanh Trung,Lap Vo in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong).

Narrative

Historical Data Imported.

Helping 647 households from Binh Thanh Trung,Lap Vo in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong). The following methods were utilized for treatment: . The following chemicals are added:

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2010 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2010 Preparation Phase

Helping 647 households from Binh Thanh Trung,Lap Vo in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong).

Narrative

Historical Data Imported.

Helping 647 households from Binh Thanh Trung,Lap Vo in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong). The following methods were utilized for treatment: . The following chemicals are added:

Impact

People Impacted: 3235

People Getting Safe Drinking Water: 3235

647.0

Member Specific Project Data

Water Source: G
Project Type: U
Treatment Type:
Chemicals Added:
Length of Pipe System (m): 9496
Comments on Status: Good
Comments on Solutions:
Notes: Good,Due to the needs increased (for 1,000 more HHs connections), PE want to have 2 more wells (460m deep) and pipeline extension (5 to 7 km)
Cost in Local Currency: 233660613.25

Funding

funded:
$10,867
Community:
$12,430
Final Cost:
$66,791
$10,867:
AusAID

Plan/Proposal