Helping 343 households from Duy Hoa ,Duy Xuyen in Vietnam access drinking water. The system is managed by the local Communal People's Committee.

Narrative

Historical Data Imported.

Helping 343 households from Duy Hoa ,Duy Xuyen in Vietnam access drinking water. The system is managed by the local Communal People's Committee. The following methods were utilized for treatment: . The following chemicals are added:

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2010 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2010 Preparation Phase

Helping 343 households from Duy Hoa ,Duy Xuyen in Vietnam access drinking water. The system is managed by the local Communal People's Committee.

Narrative

Historical Data Imported.

Helping 343 households from Duy Hoa ,Duy Xuyen in Vietnam access drinking water. The system is managed by the local Communal People's Committee. The following methods were utilized for treatment: . The following chemicals are added:

Impact

People Impacted: 1760

People Getting Safe Drinking Water: 1760

343.0

Member Specific Project Data

Water Source: S
Project Type: U
Treatment Type:
Chemicals Added:
Length of Pipe System (m): 950
Comments on Status:
Comments on Solutions:
Notes: Good,Pipeline extension (3km) for 200 more HHs connections
Cost in Local Currency: 182513500

Funding

funded:
$8,489
Final Cost:
$8,489
$8,489:
GPOBA

Plan/Proposal