Helping 9 households from Phuoc Ninh, Nhi Ha, Ca Na, Phuoc Nam, Bac Son, Loi Hai, Cong Hai, Phuoc Khang & Phuoc Chien,Thuan Nam & Thuan Bac in Vietnam access drinking water.

Narrative

Historical Data Imported.

Helping 9 households from Phuoc Ninh, Nhi Ha, Ca Na, Phuoc Nam, Bac Son, Loi Hai, Cong Hai, Phuoc Khang & Phuoc Chien,Thuan Nam & Thuan Bac in Vietnam access drinking water. . The following methods were utilized for treatment: UV light. The following chemicals are added:

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2012 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2012 Preparation Phase

Helping 9 households from Phuoc Ninh, Nhi Ha, Ca Na, Phuoc Nam, Bac Son, Loi Hai, Cong Hai, Phuoc Khang & Phuoc Chien,Thuan Nam & Thuan Bac in Vietnam access drinking water.

Narrative

Historical Data Imported.

Helping 9 households from Phuoc Ninh, Nhi Ha, Ca Na, Phuoc Nam, Bac Son, Loi Hai, Cong Hai, Phuoc Khang & Phuoc Chien,Thuan Nam & Thuan Bac in Vietnam access drinking water. . The following methods were utilized for treatment: UV light. The following chemicals are added:

Impact

People Impacted: 3506

People Getting Safe Drinking Water: 3506

0.0

Member Specific Project Data

Water Source: G
Project Type: N
Treatment Type: UV light
Chemicals Added:
Length of Pipe System (m): N/A
Comments on Status: Good
Comments on Solutions:
Notes: GOOD
Cost in Local Currency: 102020295

Funding

funded:
$4,745
Community:
$2,878
Final Cost:
$25,213
$4,745:
Diageo

Plan/Proposal