Helping 300 households from Binh Phu,Thang Binh in Vietnam access drinking water. The system is managed by a local Private Mgmnt (Center).

Narrative

Historical Data Imported.

Helping 300 households from Binh Phu,Thang Binh in Vietnam access drinking water. The system is managed by a local Private Mgmnt (Center). The following methods were utilized for treatment: sedimentation tank, vertical gravity. The following chemicals are added: chlorine

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2012 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2012 Preparation Phase

Helping 300 households from Binh Phu,Thang Binh in Vietnam access drinking water. The system is managed by a local Private Mgmnt (Center).

Narrative

Historical Data Imported.

Helping 300 households from Binh Phu,Thang Binh in Vietnam access drinking water. The system is managed by a local Private Mgmnt (Center). The following methods were utilized for treatment: sedimentation tank, vertical gravity. The following chemicals are added: chlorine

Other Issues

Unusual and unexpected issues faced during project execution

Main Problems: , , Main Reason for Problem: , , ,EMW planning, design & implementation,Other

Impact

People Impacted: 1575

People Getting Safe Drinking Water: 1575

300.0

Member Specific Project Data

Water Source: G
Project Type: N
Treatment Type: sedimentation tank, vertical gravity
Chemicals Added: chlorine
Length of Pipe System (m): 13724
Comments on Status: Good
Comments on Solutions: The donor considers to provide more fund in 2013 to install 1 more transmission line from the dam to the treatment system to get more water for the need.
Notes:
Cost in Local Currency: 1221230960

Funding

funded:
$56,801
Community:
$11,052
Final Cost:
$80,741
$56,801:
Jack Anderson

Plan/Proposal