Helping 431 households from Binh Dinh Bac,Thang Binh in Vietnam access drinking water. The system is managed by the local Communal People's Committee.

Narrative

Historical Data Imported.

Helping 431 households from Binh Dinh Bac,Thang Binh in Vietnam access drinking water. The system is managed by the local Communal People's Committee. The following methods were utilized for treatment: . The following chemicals are added:

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2009 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2009 Preparation Phase

Helping 431 households from Binh Dinh Bac,Thang Binh in Vietnam access drinking water. The system is managed by the local Communal People's Committee.

Narrative

Historical Data Imported.

Helping 431 households from Binh Dinh Bac,Thang Binh in Vietnam access drinking water. The system is managed by the local Communal People's Committee. The following methods were utilized for treatment: . The following chemicals are added:

Impact

People Impacted: 2500

People Getting Safe Drinking Water: 2500

431.0

Member Specific Project Data

Water Source: S
Project Type: N
Treatment Type:
Chemicals Added:
Length of Pipe System (m): 26103
Comments on Status: OK (but pumps often break)
Comments on Solutions:
Notes: Good
Cost in Local Currency: 1140682500

Funding

funded:
$60,422
Final Cost:
$60,422
edit $60,422:
GPOBA

Plan/Proposal