Helping 617 households from Binh Tu,Thang Binh in Vietnam access drinking water. The system is managed by the local Communal People's Committee.

Narrative

Historical Data Imported.

Helping 617 households from Binh Tu,Thang Binh in Vietnam access drinking water. The system is managed by the local Communal People's Committee. The following methods were utilized for treatment: . The following chemicals are added:

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2009 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2009 Preparation Phase

Helping 617 households from Binh Tu,Thang Binh in Vietnam access drinking water. The system is managed by the local Communal People's Committee.

Narrative

Historical Data Imported.

Helping 617 households from Binh Tu,Thang Binh in Vietnam access drinking water. The system is managed by the local Communal People's Committee. The following methods were utilized for treatment: . The following chemicals are added:

Impact

People Impacted: 3000

People Getting Safe Drinking Water: 3000

617.0

Member Specific Project Data

Water Source: G
Project Type: N
Treatment Type:
Chemicals Added:
Length of Pipe System (m): 38139
Comments on Status: good, however, the system does not have enough capacity to serve the great need in this commune
Comments on Solutions: Need new wells and pumps. Water operators need more technical and management trainings.
Notes: Good
Cost in Local Currency: 1241281000

Funding

funded:
$57,734
Final Cost:
$57,734
edit $57,734:
GPOBA

Plan/Proposal