Monitor water quality at the STP.
Narrative
Project to monitor STP operations and treated water quality.
Sewage Treatment Plant Data
No specific STP design or operating data- Impact Assessment (M&E) Phase Project completed on 31 Dec, 2010 Implementation Phase
- Implementation Phase Project started on 1 Jan, 2009 Preparation Phase
Monitor water quality at the STP.
Narrative
Project to monitor STP operations and treated water quality.
Sustainability
Creating and measuring long-term impact
Monthy costs in energy and staff
Impact
People Impacted: 2000
People Getting Other Benefits: 2000
Daily number of visitors to hospital plus resident staff
Maintenance/Operating Costs Annual, in US$: $1000
Creating and measuring long-term impact
Monthy costs in energy and staff
Funding
- funded:
- $40,000
- Community:
- $40,000
- Final Cost:
- $40,000