Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.

Narrative

Once again the site got cancelled after the successful village mtg when the spot was finalized but later due to dispute over the land got cancelled. The new site is at Toronipur village of Gobindopur Panchayet in the Swarupnagar Block of N 24 Parganas. The land is donated by Belayet Mondol.

____________________________________
This site #PW219 is now finalized. It is in the village of Gobindopur of Swarupnagar block of N24 Parganas. The land is donated by Niranjan Sarkar.

___________________________
This site got cancelled - site in Kanakpur village of Swarupnagar block of North 24 Parganas district. This site will be confirmed after pilot test.

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed Wed 10 Jul 2013, Over 11 Years ago

    i am doing demography

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed Mon 05 Nov 2012, Almost 12 Years ago

    this well is used by 8 families 42people

  • Impact Assessment (M&E) Phase Project completed on 31 Oct, 2012 Implementation Phase
  • Biswajit Karmakar of Project Well
    • confidential
    Implementation Status: completed Wed 04 Jul 2012, Over 12 Years ago

    Follow UP

    PW219 - the land has been donated by Samad Sardar and the dug well construction is completed. The marble slab is been put up by the workers by 6th july 2012.

    • PW219.JPG
  • Meera Hira-Smith of Project Well
    • confidential
    Implementation Status: in_progress Fri 01 Jun 2012, Over 12 Years ago

    Construction of the bore-dugwell is complete

    Construction of the bore-dugwell is complete

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: in_progress Fri 30 Mar 2012, Over 12 Years ago

    Village meeting is success. 32 people attended this village meeting. Donor of the land to construct dugwell is Niranjan Sarkar of Swarupnagar.

  • Implementation Phase Project started on 1 Nov, 2011 Preparation Phase

Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.

Narrative

Once again the site got cancelled after the successful village mtg when the spot was finalized but later due to dispute over the land got cancelled. The new site is at Toronipur village of Gobindopur Panchayet in the Swarupnagar Block of N 24 Parganas. The land is donated by Belayet Mondol.

____________________________________
This site #PW219 is now finalized. It is in the village of Gobindopur of Swarupnagar block of N24 Parganas. The land is donated by Niranjan Sarkar.

___________________________
This site got cancelled - site in Kanakpur village of Swarupnagar block of North 24 Parganas district. This site will be confirmed after pilot test.

Impact

People Getting Safe Drinking Water: 40

Registers will be created as soon as the community starts using the water from this bore-dugwell.

Maintenance/Operating Costs Annual, in US$: $40

Creating and measuring long-term impact

Implementer: Project Well & Aqua Welfare Society

Aqua Welfare Society (AWS) is the partner NGO of Project Well.

Funding

funded:
$1,073

Plan/Proposal