Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
Finally this bore-dugwell #PW231 is constructed in the premises near the masjit beside the grocery store of Monta in the south hyderpur village under the jurisdiction of Baduria Panchayet.
___________________________________
New site in North 24 Parganas in the Baduria Block. This bore-dugwell #PW231 is in the Gobra village under the jurisdiction of Gobindopur Panchayet and the land belongs to the Club in Gobra. Pilot test and village meetings are pending.
________________________________________
This site #PW231, is in the Madhyapara village of Ranaghat block in Nadia district. The site was donated by Masjid near Monta's Shop. This site got cancelled after the village meeting just before the pilot test when the panchayet notified about pipeline water supply to be installed soon in that area.
-
Suparna Mondol of Project WellImplementation Status: completed Wed 18 Sep 2013, About 11 Years ago
We went to inspect the dugwell no- pw-231.
-
Suparna Mondol of Project WellImplementation Status: completed Thu 12 Sep 2013, About 11 Years ago
We went to inspect the dugwell no- pw-230.
-
Meera Hira-Smith of Project WellImplementation Status: completed Mon 26 Nov 2012, Almost 12 Years ago
PW231:Visited by Meera Smith and Laltu Midhya to collect water sample to test for arsenic and for inspection.
Ms. Tuhina Khatun says that many people from the community takes water from this bre-dugwell about 15 to 20 families. and she also testifies that nobody has complaint about the water being undrinkable. They all like the taste of the water.
unable to embed so please copy/paste this video link> http://youtu.be/F5Tn_c50JgY - Impact Assessment (M&E) Phase Project completed on 31 Oct, 2012 Implementation Phase
- Implementation Phase Project started on 1 Nov, 2011 Preparation Phase
Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
Finally this bore-dugwell #PW231 is constructed in the premises near the masjit beside the grocery store of Monta in the south hyderpur village under the jurisdiction of Baduria Panchayet.
___________________________________
New site in North 24 Parganas in the Baduria Block. This bore-dugwell #PW231 is in the Gobra village under the jurisdiction of Gobindopur Panchayet and the land belongs to the Club in Gobra. Pilot test and village meetings are pending.
________________________________________
This site #PW231, is in the Madhyapara village of Ranaghat block in Nadia district. The site was donated by Masjid near Monta's Shop. This site got cancelled after the village meeting just before the pilot test when the panchayet notified about pipeline water supply to be installed soon in that area.
Other Issues
Unusual and unexpected issues faced during project execution
The large diameter (10”) pipes for 25 bore dugwells have arrived within 3 weeks after placing the order. The construction team is engaged in conducting site selection procedures while the awareness team is continuing with awareness programs in schools and communities in the areas where dugwells are in operation.
Learnings
Knowledge of project and process for sharing
It is very important that the public health & engineering government offices of West Bengal make the detail map of pipeline with exact names of the villages and paras available to NGO's who are working in the area.
Impact
People Getting Safe Drinking Water: 40
Registers will be created as soon as the community starts using the water from this bore-dugwell.
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society (AWS) is the partner NGO of Project Well.
Funding
- funded:
- $1,073