Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.

Img_0163

Narrative

This site #PW239, is in chougacha village of Deuli panchayat of Chakdah block of Nadia district. The land is donated by Anil Chandra Das. Village meeting pending.

    • SMS
    Ranajit Bala ( Project Well ) 9 Months after completion 3 Aug, 2013

    Operating Status:

    people are not drinking due to iron.

    • SMS
    Ranajit Bala ( Project Well ) 8 Months after completion 3 Jul, 2013

    Operating Status:

    Too much Iron in water so people are not using now. but 4 families are using only for other domestic purpose.

    • SMS
    Ranajit Bala ( Project Well ) 6 Months after completion 8 May, 2013

    Operating Status:

    HEALTH MEETING IS OK.PEOPLE FE 10 ME 3 CHI2

    • SMS
    Farida Bibi ( Project Well ) 8 Days after completion 8 Nov, 2012

    Operating Status:

    this well is used by 4 families 16 people

  • Impact Assessment (M&E) Phase Project completed on 31 Oct, 2012 Implementation Phase
    Meera Hira-Smith ( Project Well ) 6 Months after start 13 Oct, 2012

    Construction is complete

    Status: Complete - Successful

    Operating Status:

    People are using the water. And please see the final report document uploaded as pdf here> http://peerwater.org/en/projects/740.

    Pictures will be uploaded by this week.

  • Implementation Phase Project started on 2 Apr, 2012 Preparation Phase

Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.

Narrative

This site #PW239, is in chougacha village of Deuli panchayat of Chakdah block of Nadia district. The land is donated by Anil Chandra Das. Village meeting pending.

Impact

People Getting Safe Drinking Water: 49

According to the report of March 2013 12 families are using water from this well.

Registers will be created as soon as the community starts using the water from this bore-dugwell.

Maintenance/Operating Costs Annual, in US$: $40

Creating and measuring long-term impact

Implementer: Project Well & Aqua Welfare Society

Aqua Welfare Society (AWS) is the partner NGO of Project Well.

Funding

Funded:
$1,246
$1,246:
Arghyam

Plan/Proposal