Construction of an Underground Rainwater Harvesting Tank at the Church of God of Prophecy Primary School in Makosseh/Port Loko District with more 4800 beneficiaries.
Narrative
Could not start as proposed.
- Impact Assessment (M&E) Phase Project completed on 15 Aug, 2006 Implementation Phase
- Implementation Phase Project started on 15 May, 2006 Preparation Phase
Construction of an Underground Rainwater Harvesting Tank at the Church of God of Prophecy Primary School in Makosseh/Port Loko District with more 4800 beneficiaries.
Narrative
Could not start as proposed.
Sustainability
Creating and measuring long-term impact
Revenue collected will be used to chlorinate and refill the tank.
Other Issues
Unusual and unexpected issues faced during project execution
Training in maintenance of the tank
Learnings
Knowledge of project and process for sharing
water plays a vital role in sanitation and improving peoples lives.
Impact
People Getting Safe Drinking Water: 4800
806 students of the institution
about 4000 indirect beneficiaries within 10 settlements around the school
School Children Getting Water: 806
People Getting Sanitation: 4806
People Getting Other Benefits: 20
15 workers employed for the construction
5 people got water/sanitation education to take care of the system
Maintenance/Operating Costs Annual, in US$: $20
Creating and measuring long-term impact
Revenue collected will be used to chlorinate and refill the tank.
Funding
- funded:
- $9,800
- Final Cost:
- $9,822
- $9,800:
- Blue Planet Network