plan 9RWHT at Safer Future Vocational Institute, Allentown
-
Implementation Dates:
Oct 2005 to
Jan 2006
Focus: Drinking Water - Schools
and Drinking Water - Community
Planned Impact: 1,700 people
-
Status: Plan accepted
-
Peer Review
Reviewers Assigned: 2
Reviews Submitted: 0
Discussion Participants: 5
Map of Plan & Projects
Summary
Construction of an Underground Rainwater Harvesting Tank at the Safer Future Vocational Institute, Allen/Town Freetown with more 1500 beneficiaries.
Background
Allentown lies at a sloppy hill with rocky ground. Therefore it is not possible to dig water wells since solid rock is very near to the surface. tThe only way to get water is to climb down the hill to streams in the mangroves. The quality of the water the
Location
Western Area,
Freetown,
Sierra Leone
Attachments
-
IMG_1307...
-
IMG_0907...
-
IMG_0473...
-
budget_s...
Focus
Primary Focus: Drinking Water - Schools
Secondary Focus: Drinking Water - Community
People Getting Safe Drinking Water:
1,700
200 students of the institution
about 1500 indirect beneficiaries within the community
School Children Getting Water:
200
People Getting Sanitation:
0
Pure drinking water project
People Getting Other Benefits:
Start Date: 2005-10-31
Completion Date: 2006-01-31
Technology Used:
Underground Rainwater Harvesting Tank equipped with an Indian Mark II hand pump and connected to the schools roof.
Phases:
Done in one phase
Community Organization:
As usual, a committee is formed to supervise the usage of the infrastructure. The committee consists of 7 members representing the Vocational Institute (Students Representative, Health Representative, Project Manager) and the Community (Chairman, Nurse)
Since this tank is located at the Vocational Institute of the Implementing Agency it will have a representing role. It will serve as example for visitors from other organisations as well as other interested persons.
Government Interaction:
Ancillary activities:
Training in Health Care and Nutrition done by Safer Future
Other Issues:
This will be the pilot project for implementing RWHT of this kind by Safer Future
Maintenance Revenue:
Usage Fees:
Students: 500 Leone (20 US-Cent)
Everybody else: 200 Leone per Bucket (8 US-Cent)
Maintenance Cost:
Metrics:
Prior art before metrics
Cost: $10,020
Material Cost SLL 18.035.000
Activity Cost SLL 5.404.000
Administrative Cost SLL2.400.000
Total SLL 25.839.000/$10.019/€8.335
Co Funding Amount: $0
none
Community Contribution Amount:
Community takes care about maintenance
Fund Requested: $10,020
Attachments
-
IMG_1307...
-
IMG_0907...
-
IMG_0473...
-
budget_s...
-
Unfortunately there was a typing mistake while entering the data. The total Project Costs as well as the funds applied for should be USD 10,020
Unfortunately there was a typing mistake while entering the data. The total Project Costs as well as the funds applied for should be USD 10,020
-
Is this the project funded by BPR in 2004 and needed a small amount to complete? If so, this should be in the 2004 funding cycle (need to create that) and have the total reflect the amounts funded in 2004 and 2005.
Is this the project funded by BPR in 2004 and needed a small amount to complete? If so, this should be in the 2004 funding cycle (need to create that) and have the total reflect the amounts funded in 2004 and 2005.
-
Idriss Kamara of Safer Future Youth Development Project
no, it was a 2005 project...
maybe I made a mistake entering it as seperate project... phase 1 was the tank at the faith in christ school, phase 2 was this tank. The funds for this tank were requested and received in 2005
Tobias
no, it was a 2005 project...
maybe I made a mistake entering it as seperate project... phase 1 was the tank at the faith in christ school, phase 2 was this tank. The funds for this tank were requested and received in 2005
Tobias
-
Rajesh Shah of Blue Planet Network
You are right that the funds were received in 2005. However, for the foundation paperwork we had budgeted phase2 in 2004. Since Safer Future was a new and unknown organization to us, we felt it too risky to fund the entire project.
Also, i believe even phase I went overbudget and we helped out to complete it.
You are right that the funds were received in 2005. However, for the foundation paperwork we had budgeted phase2 in 2004. Since Safer Future was a new and unknown organization to us, we felt it too risky to fund the entire project.
Also, i believe even phase I went overbudget and we helped out to complete it.
-
Idriss Kamara of Safer Future Youth Development Project
Yes, the project was proposed and also funded in 2004. Phase1 (Faith in Christ) was finished beginning 2005 with the exception of the pump. Phase2 was started in the second half of 2005 and both tanks were finally finished January 2006
Yes, the project was proposed and also funded in 2004. Phase1 (Faith in Christ) was finished beginning 2005 with the exception of the pump. Phase2 was started in the second half of 2005 and both tanks were finally finished January 2006
-
Rajesh Shah of Blue Planet Network
You are right that the funds were received in 2005. However, for the foundation paperwork we had budgeted phase2 in 2004. Since Safer Future was a new and unknown organization to us, we felt it too risky to fund the entire project.
Also, i believe even phase I went overbudget and we helped out to complete it.
You are right that the funds were received in 2005. However, for the foundation paperwork we had budgeted phase2 in 2004. Since Safer Future was a new and unknown organization to us, we felt it too risky to fund the entire project.
Also, i believe even phase I went overbudget and we helped out to complete it.
-
Idriss Kamara of Safer Future Youth Development Project
Yes, the project was proposed and also funded in 2004. Phase1 (Faith in Christ) was finished beginning 2005 with the exception of the pump. Phase2 was started in the second half of 2005 and both tanks were finally finished January 2006
Yes, the project was proposed and also funded in 2004. Phase1 (Faith in Christ) was finished beginning 2005 with the exception of the pump. Phase2 was started in the second half of 2005 and both tanks were finally finished January 2006