Helping 415 households from Dien Phong,Dien Ban in Vietnam access drinking water. The system is managed by the local Communal People's Committee.

Narrative

Historical Data Imported.

Helping 415 households from Dien Phong,Dien Ban in Vietnam access drinking water. The system is managed by the local Communal People's Committee. The following methods were utilized for treatment: pressure.

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2006 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2006 Preparation Phase

Helping 415 households from Dien Phong,Dien Ban in Vietnam access drinking water. The system is managed by the local Communal People's Committee.

Narrative

Historical Data Imported.

Helping 415 households from Dien Phong,Dien Ban in Vietnam access drinking water. The system is managed by the local Communal People's Committee. The following methods were utilized for treatment: pressure.

Sustainability

Creating and measuring long-term impact

Treatment, Electro-mechanical (pumps, etc.), Groundwater quality, ,

Other Issues

Unusual and unexpected issues faced during project execution

Main Problems: , , , ,Treatment Main Reason for Problem: , , ,EMW planning, design & implementation,Water quantity/quality declined over time

Impact

People Impacted: 1867

People Getting Safe Drinking Water: 1867

Member Specific Project Data

Water Source: G
Project Type: N
Treatment Type: pressure
Chemicals Added:
Length of Pipe System (m): 12630
Comments on Status: non operational
Comments on Solutions:
Notes: Good
Cost in Local Currency: 475601500

Funding

funded:
$22,121
Final Cost:
$22,121
edit $22,121:
Jack Anderson

Plan/Proposal