Summary
Proposal already approved and funded, this application is placeholder for importing existing projects
Background
Proposal already approved and funded, this application is placeholder for importing existing projects
Implementation Dates: Jan 2006 to Dec 2006
Focus: Capacity Building
and Other
Planned Impact: 19,818 people
Plan Amount: | 341,145 |
Amount Funded: | 336,717 |
Funded by: | |
Gap Inc. | 47,988 |
Anonymous | 73,431 |
Rotary Clubs | 48,415 |
Jack Anderson | 22,121 |
Janet McKinley and George Miller | 123,362 |
Cathay Pacific | 21,400 |
Plan Not Peer Reviewed
Proposal already approved and funded, this application is placeholder for importing existing projects
Proposal already approved and funded, this application is placeholder for importing existing projects
Name | Status | Completion Date | Final Cost |
---|---|---|---|
Phuoc Am | completed | Dec 2006 | 27,900 |
Quang Dien | completed | Dec 2006 | 13,000 |
Duc Hoa | completed | Dec 2006 | 40,309 |
Thon 6, Tam Hai | completed | Dec 2006 | 10,000 |
Group 7&8 - Trieu Chau | completed | Dec 2006 | 11,415 |
Cam Phu I, II | completed | Dec 2006 | 22,121 |
Ba Bau | completed | Dec 2006 | 29,098 |
Cam Dong | completed | Dec 2006 | 19,224 |
Dai Son - Dong Giang | completed | Dec 2006 | 20,088 |
La Thap Tay | completed | Dec 2006 | 21,400 |
Lang Chau Bac | completed | Dec 2006 | 16,622 |
Thanh Xuyen | completed | Dec 2006 | 20,493 |
Xom Chua | completed | Dec 2006 | 3,500 |
Tu Tra | completed | Dec 2006 | 27,000 |
Loc Binh | completed | Dec 2006 | 12,802 |
Dong My, Dong Binh, Thuan An (WS #4) | completed | Dec 2006 | 19,608 |
ThuongVinh,Tan My and Phu My | completed | Dec 2006 | 26,565 |