Providing facilitation support to Village Water Committees, social mobilisation and awareness generation and capacity building
Narrative
To be completed by CSPC/ SRTT
- Impact Assessment (M&E) Phase Project completed on 31 Dec, 2011 Implementation Phase
- Implementation Phase Project started on 1 Jan, 2011 Preparation Phase
-
Divyang Waghela of Coastal Salinity Prevention CellImplementation Status: completed Fri 30 Apr 2010, Over 14 Years ago
Baseline Study Report
Centre for Intergrated Development, Ahmedabad helped put together a project report on Tata-GE special drinking water supply and sanitation. The report updates the current condition related to water and sanitation in the villages. Major findings of the baseline study are:
a) Demographic details and household pattern
b) Livelihood pattern
c) Water scenario
d) Sanitation, waste management and other amenities
e) Personal hygiene and behavioral aspects
f) Health & Education condition.Detailed report attached in the project ID 344 - http://peerwater.org/projects/344
-
Divyang Waghela of Coastal Salinity Prevention CellImplementation Status: completed Mon 04 May 2009, Over 15 Years ago
Baseline study launched
The project will cover 10 villages across Mangrol block of Junagadh district and Porbandar block of Porbandar district. A total of about 5000 households (app 25,000 beneficiaries) would be covered across 8 villages.
The major activities planned in each village are:
• Community level capacity building initiatives for construction, operation and maintenance of the RO based drinking water supply units;
• Training and capacity building inputs
• Comprehensive village level drinking water storage and supply network;
• Construction of individual HH level sanitation units, compost pits, soak pits, biogas/ NADEP units / smokeless chullahs.Major expected outcome of the project is to:
• improve access to drinking and domestic water needs through provision of treated potable water & substantial reduction in drudgery and time of women for fetching domestic water.
• Promote improved hygiene and sanitation practices
Providing facilitation support to Village Water Committees, social mobilisation and awareness generation and capacity building
Narrative
To be completed by CSPC/ SRTT
Sustainability
Creating and measuring long-term impact
To be completed by CSPC/ SRTT
Other Issues
Unusual and unexpected issues faced during project execution
To be completed by CSPC/ SRTT
Learnings
Knowledge of project and process for sharing
To be completed by CSPC/ SRTT
Impact
Implementer: Ambuja Cement Foundation
Funding
- funded:
- $338,486
- Community:
- $77,613
- Final Cost:
- $338,486