The project will consist of the construction of a spring box ; conduction line of 5.2 km; a 5 cubic meter storage tank;and repairs of an existing storage tank.

Narrative

The Pulay Water Project is complete with all elements of the project installed and functioning. The project is two weeks ahead of schedule with the finish. In consultation with the village water committee and Rahesh the plan is to enclose another spring site that the village has recently purchased so as to make this water available for future needs. The village has been very cooperative and raised about Q35,000 ($5,000) during the project and with these funds made a number of improvements to their distribution system the the houses in the village. We anticipate being finished by the end of Jan. with the project.

  • Lynn Roberts of Agua Para La Salud (APLS)
    • confidential
    Implementation Status: in_progress Thu 15 Jan 2009, Almost 16 Years ago

    Pulay Water System

    The project was finished two weeks early with all of the original elements of the project completed and functioning. In consultation with the village water committee and Rahesh the plan is to capture another spring site and repair a large public water station. The project should be finished by the end of Jan.

  • Impact Assessment (M&E) Phase Project completed on 15 Jan, 2009 Implementation Phase
  • Implementation Phase Project started on 20 Oct, 2008 Preparation Phase

The project will consist of the construction of a spring box ; conduction line of 5.2 km; a 5 cubic meter storage tank;and repairs of an existing storage tank.

Narrative

The Pulay Water Project is complete with all elements of the project installed and functioning. The project is two weeks ahead of schedule with the finish. In consultation with the village water committee and Rahesh the plan is to enclose another spring site that the village has recently purchased so as to make this water available for future needs. The village has been very cooperative and raised about Q35,000 ($5,000) during the project and with these funds made a number of improvements to their distribution system the the houses in the village. We anticipate being finished by the end of Jan. with the project.

Sustainability

Creating and measuring long-term impact

We are currently working with the village to develop a maintenance program including the new facilities.

Other Issues

Unusual and unexpected issues faced during project execution

A second phase of this project is planned provided funds can be found. During the project a study was done of the distribution system to the houses. Thefindings indicated that about 90 families were not connected to the water system. We have developed a plan and design to renovate the entire water distribution system to provide sufficient flow to all the houses for a period of 20 years utilizing the old and new springs on line in the village.

Learnings

Knowledge of project and process for sharing

See final report

Impact

People Getting Safe Drinking Water: 2100

Our original submission indicated that there were about 250 families in the village. During the project the village water committee indicated that they had only given us the number of families connected to the system. In reality many young families living with parents and families not connect to the system raised the total number of families to about 350.

People Getting Other Benefits: 2100

Health and higiene education was carried out housey house and in public meetings.

Maintenance/Operating Costs Annual, in US$: $300

Creating and measuring long-term impact

We are currently working with the village to develop a maintenance program including the new facilities.

Funding

funded:
$24,761
Final Cost:
$26,884

Plan/Proposal