: Bore hole construction to London and Mbulani Secondary School

Applicant Tanzania Mission to the Poor and Disabled (PADI) Plan ID: 198
Status: approved_accepted Review Cycle end date: 2009-08-29

Discussion Forum

Budget question

By Peer Water Exchange Posted on Wed 19 Aug 2009, almost 17 years ago

Please see the other application for 2 village bore wells for question and post a response on that for both applications.

Review process

By Peer Water Exchange Posted on Wed 05 Aug 2009, almost 17 years ago

This application will not go thru peer review.
It will get a combination of 3 results:
- the peer review of a similar application last year
- the peer review of this years application
- the reports and results of the 3 projects:
Kalembo,,
Luwawasi,, and
Chandarua,
funded last year.

Please fix the sanitation numbers to zero as this project does not involve installing sanitation facilities.

Also, check out the rope pump video on HPPI profile and their application. Maybe that can be used here.

Review process

By Tanzania Mission to the Poor and Disabled (PADI) Posted on Wed 12 Aug 2009, almost 17 years ago

Thank you very much for your advice Mr Rajesh, I have acted on it. I have changed the number of people geting santation as you have advised.
Regards
Msigwa


Application Summary

Applicant :   Tanzania Mission to the Poor and Disabled (PADI)
Status : approved_accepted
Country : TANZANIA Map

Funding

Amount Funded :   $12,886
Funded By:-
MSSCT : $12,886
Funds Used
: $12,886
Funds Available
: $0

Projects Summary of Application

Number of Projects : 2
Overall Start Date : TODO!
Overall Completion Date : TODO!
Date of Last Update : 2010-01-24