Projects of: " Bore hole construction to London and Mbulani Secondary School"

Applicant Tanzania Mission to the Poor and Disabled (PADI) Plan ID: 198
Status: approved_accepted Review Cycle end date: 2009-08-29

Name Status Start Date Completion Date Date of Last Report Amount Assigned
Borehole for Londoni secondary school, Songea completed 2009-11-15 2010-02-15 2010-01-24 $6,443
Borehole for Mbulani secondary school, Songea completed 2009-11-21 2010-02-15 2010-01-24 $6,443

Application Summary

Applicant :   Tanzania Mission to the Poor and Disabled (PADI)
Status : approved_accepted
Country : TANZANIA Map

Funding

Amount Funded :   $12,886
Funded By:-
MSSCT : $12,886
Funds Used
: $12,886
Funds Available
: $0

Projects Summary of Application

Number of Projects : 2
Overall Start Date : TODO!
Overall Completion Date : TODO!
Date of Last Update : 2010-01-24