plan 349Well construction in 8 villages in Samburu District (D2W1 to D2W8)

Summary

The Samburu Project brings wells to communities in Milamani, Wamba, Logovisho, Embasani, Lorian, Lower Sordo, Lopesiwo villages which otherwise suffer the health and livelihood consequences of being without water. Our wells enhance the lives of thousands.

Background

Proposal submitted and funded outside PWX

Location

Milamani, Samburu, Kenya

Focus

Primary Focus: Drinking Water - Community
Secondary Focus: Sanitation - Community

People Getting Safe Drinking Water: 8,750

The main objective of the project is to provide clean, safe drinking water.

School Children Getting Water:

People Getting Sanitation: 8,750


Improved sanitation has been an ancillary benefit of community water availability.

People Getting Other Benefits:

Start Date: 2007-07-01

Completion Date: 2007-07-31

Technology Used:

Proposal submitted and funded outside PWX

Phases:

Proposal submitted and funded outside PWX

Community Organization:

Proposal submitted and funded outside PWX

Government Interaction:

Proposal submitted and funded outside PWX

Ancillary activities:

Proposal submitted and funded outside PWX

Other Issues:

Proposal submitted and funded outside PWX

Maintenance Revenue:

Maintenance Cost: $3,280

Metrics:

Prior art before metrics

Cost: $116,950

to be updated

Co Funding Amount:

Community Contribution Amount: $12,950

Fund Requested: $104,000

Name Status Completion Date Final Cost
D2W1: Milimani Well completed Jul 2007 12,350
D2W2: Wamba DEB Primary School Well completed Jul 2007 12,350
D2W3: Logoricho Well completed Jul 2007 12,350
D2W4: Embakasi Well completed Jul 2007 12,350
D2W5: Lorian/Golgoltim Well completed Jul 2007 12,350
D2W6: Lower Sordo Well completed Jul 2007 12,350
D2W7: Lopesiwo 2 Well completed Jul 2007 12,350
D2W8: Lopesiwo 3 Well completed Jul 2007 12,350